MAN Energy Solutions has announced the successful first running of a test engine on ammonia at its Research Centre Copenhagen (RCC).
The company reports that the successful combustion was performed on a MAN B&W two-stroke 4T50ME-X type and produced positive results with particularly promising data regarding pilot-oil amount and combustion stability.
First ammonia engine test completed
Gunnar Stiesch, the Chief Technical Officer, MAN Energy Solutions, said: “This marks a major milestone on our road to developing a full-scale two-stroke ammonia marine engine. It’s been a historic week for our team at the RCC, where a lot of groundwork and research has now paid off, and we have gained a deep understanding of ammonia’s unique characteristics as a marine fuel, as well as its effects on fuel supply and safety systems.”
MAN Energy Solutions reports that safety has been of paramount importance at all stages
Gunnar Stiesch adds, “This successful combustion represents yet another, important step towards decarbonising the marine market and bringing big things to zero.”
MAN Energy Solutions reports that safety has been of paramount importance at all stages leading to the new milestone. Precautions taken due to the fuel’s inherent characteristics include the construction of a custom-built ‘cold hall’, which can contain ammonia vapour in the unlikely event of a leak with the activation of a water screen.
Robust safety features
Robust safety features from the company’s existing dual-fuel portfolio, such as double-walled piping and system ventilation, have also been built into the ammonia engine’s design.
Brian Østergaard Sørensen, the Vice President and Head of Research & Development, Two-Stroke at MAN Energy Solutions, said: “This is groundbreaking for both our company and the maritime industry as a whole. That said, we know we still have a lot of hard work ahead and, over the following months, will execute a testing programme that will study aspects such as heat-release, ignition, safety, pilot-oil energy fraction, NOx and N2O emissions.”
Study aspects such as heat-release, ignition, safety
MAN Energy Solutions states that it broadly expects to hold its delivery timeline for the first ammonia engine
Brian Østergaard Sørensen adds, “We then plan on rebuilding the test engine from one cylinder capable of running on ammonia to a full-scale test engine running on ammonia around the end of this year or early in 2024.”
MAN Energy Solutions states that it broadly expects to hold its delivery timeline for the first ammonia engine, with subsequent operation onboard a commercial vessel from around 2026.
Move to decarbonise the maritime industry
Bjarne Foldager, the Head of Two-Stroke Business, MAN Energy Solutions, said: “Interest in this breakthrough has been overwhelming. However, while we provide the decarbonising technology, the maritime industry must show the will to implement it. Now it’s up to the International Maritime Organization to establish clear regulations that ensure that maritime actors are not penalised for choosing carbon-neutral fuels.”
Bjarne Foldager adds, “At MAN Energy Solutions, our expectations for ammonia are positive owing to its predicted lower production cost compared to other, relevant e-fuels; we foresee around 27% of fuel used onboard large merchant-marine vessels to be ammonia by 2050.”
MAN B&W ammonia engine
Thomas S. Hansen, the Head of Promotion and Customer Support, MAN Energy Solutions, said: “The first MAN B&W ammonia engine will be a 60-bore engine, which will be applicable to a very wide range of vessel types.”
MAN Energy Solutions expects a quick uptake of ammonia-fuelled engines towards the end of the current decade"
Thomas S. Hansen adds, “The interest in this engine is very high and we have received many queries across basically all large merchant-marine vessels. MAN Energy Solutions expects a quick uptake of ammonia-fuelled engines towards the end of the current decade.”
Project steps
The ammonia engine R&D project started in 2019 with a pre-study and investigation of ammonia combustibility. The following year, a second test-engine arrived in Copenhagen, enabling a parallel-test engine setup with different fuels at RCC; HAZID workshops on the engine concepts were performed simultaneously.
In 2021, the ammonia fuel-supply system and auxiliary systems were specified with the highest possible focus on safety, while 2022 saw the installation of the same systems at RCC with instrumentation for test engine No. 1 for 1-cylinder ammonia testing initiated.
Ammonia bunkering and service-tank facilities
In 2023, ammonia bunkering and service-tank facilities were built with all auxiliary systems enabling a full containment of ammonia in the unlikely event of a leak. Similarly, all auxiliary systems were initially tested with water, followed by ammonia.