Download PDF version

Goltens Singapore was contracted by a well known LNG Ship owner to execute 3D scanning, design engineering, material supply & installation supervision on one of their vessels.

The BWTS installation comprises of one of the world’s largest Ballast Water Treatment System to be installed onboard vessel to comply with IMO regulations.

3D laser scanning

Detailed scope of work:

  • 3D scanning & vessel survey.
  • Basic and Detail engineering.
  • Class approvals.
  • Procurement & Prefabrication.
  • Supply of Material to Shipyard (Big Bore piping, Small Bore piping, Site run Piping & fittings, Valves & Cable Drums).
  • Installation supervision.

Upon contract agreement, Goltens Singapore performed 3D laser scanning with a team of proficient engineers onboard the vessel. Upon completion, the 3D scans were registered and Goltens Singapore embarked on the design engineering works with 3D modelling software. Goltens Singapore worked rigorously to develop the Engineering Design and upon approval from vessel representatives & class the prefabrication & procurement of materials & equipment respectively was begun.

Conducting numerous inspections

The installation was carried out by Sembawang Shipyard Contractors for a duration of 20 days

From the outset, the primary constraint of the project was the limited size of area surrounding the ballast pumps as the Maker’s (TechCross) equipment were both large in size and quantity. Despite these constraints, the engineering team scrutinised the designs repeatedly to ensure that the design was able to optimise the space management.

During the prefabrication phase, Goltens Singapore Team conducted numerous inspections to ensure that the quality & integrity of prefabricated pipes were up to satisfactory standards. Upon completion of pre-fabrication, Non- Destructive Testing was carried out by qualified Goltens personnel and witnessed by Vessel representatives. The installation was carried out by Sembawang Shipyard Contractors for a duration of 20 days & was completed successfully.

Power distribution equipment

The installation phase was carried out in 5 different stages simultaneously.

  • Stage 1: Remove the existing pipes to install the tie in spools, lift out the existing pipes (demolition) and install the newly fabricated big bore (600A) pipes.
  • Stage 2: Fabricate & install the foundation supports for the equipment (electro chamber unit, power distribution equipment, auto neutralisation unit & TRO sensor unit)
  • Stage 3: Lifting the equipment safely into the lowest deck of the Engine Room and securing the equipment.
  • Stage 4: Completion of electrical works including: cable pulling, cable termination at main switchboards, power distribution equipment and equipment onsite.
  • Stage 5: Installation of the small-bore piping between the equipment and big bore spools. Over the entire installation phase, Goltens Singapore guided the shipyard contractors meticulously to ensure there were no delays to the project schedule and that it was completed on time.

Over the entire installation phase, Goltens Singapore guided the shipyard contractors meticulously to ensure there were no delays to the project schedule and that it was completed on time.

Download PDF version Download PDF version

In case you missed it

Cummins showcases marine technology solutions at International Workboat Show 2024
Cummins showcases marine technology solutions at International Workboat Show 2024

Cummins Inc., a global pioneer in power solutions, will exhibit its latest marine technologies at the International Workboat Show 2024, in New Orleans, from November 12-14, 2024.&n...

LEO networks revolutionise maritime connectivity
LEO networks revolutionise maritime connectivity

Maritime communications came a long way before they could deliver the first Global Maritime Distress and Safety System (GMDSS). Still, it is fair to say that their forward march ha...

E-methane offers environmental, compliance, and performance advantages
E-methane offers environmental, compliance, and performance advantages

As the maritime industry accelerates its journey toward decarbonisation, the focus on alternative fuels has intensified. E-methane E-methane, a synthetic gas produced using renew...

vfd