The cargo ship SE Cerulean suffered a major crankshaft failure on its port side main engine. As the maximum allowable undersize for this crankshaft was only 2.0mm, the owner decided to replace the crankshaft rather than try to salvage it by machining.

Planning & preparation

After surveying the vessel for rigging logistics, Goltens prepared all required lifting brackets and rigging gear at its workshop and reviewed the repair schedule and timeline with the customer. Goltens then mobilised the tools and a team capable of working non-stop to Keppel shipyard to effect the repairs.

Engine dismantling

All main engine components – cylinder heads and liners, pistons, connecting rods, fuel pumps and injectors, lube oil and fresh water pumps, and air cooler were dismantled and brought to Goltens’ workshop for inspection and control measurements. The engine block was lifted and the old crankshaft removed and sent to the Goltens workshop for the survey.

Crankshaft replacement and rebuild

Goltens laser aligned the engine and completed Chockfasting of the engine foundation

The new crankshaft was inspected in the presence of the surveyor at Goltens’ workshop and all the measurements were well within the maker’s tolerances.

The crankshaft was then transferred to the vessel and contact tests between the crankshaft webs and counterweights were completed. The flywheel and vibration were dampers fitted and reaming of the fitted bolts holes completed. Old crankshaft gear from the condemned shaft was transferred to the new shaft as per maker guidelines.

The new crankshaft was then rigged into the engine room and assembled with new bearings. The engine was then rebuilt with the components overhauled at the workshop. New connecting rods were installed after cracks were discovered in the serrations. As final preparations for engine commissioning and testing, Goltens laser aligned the engine and completed Chockfasting of the engine foundation.

Sea trial and results

After flushing the internal and external lube oil systems, the running in program and load trials were completed per maker guidelines.

The vessel completed an engine trial in the basin followed by a full sea trial at 100% load. The full repair was completed per the planned schedule and the vessel returned to service.

Customer comment

“M/V Cerulean sailed out today morning with successful repair of the port engine. I would like to thank your entire team for exceptional support from the office and workshop. Very well job done!!!”

Download PDF version Download PDF version

In case you missed it

Marine biofuels: The future of eco-friendly shipping
Marine biofuels: The future of eco-friendly shipping

In a major push toward decarbonising maritime logistics, President Jae-young Byeon of the Ulsan Port Authority (UPA) and Chief Executive Sun-bae Hong of the Korea Maritime Cooperat...

How American sanctions may affect the global shipping industry
How American sanctions may affect the global shipping industry

President Donald Trump has already made plenty of headlines since taking up his second term in the White House, including with the announcement of numerous new tariffs on imports....

ABS sets safety benchmark in marine industry
ABS sets safety benchmark in marine industry

In recognition of its exceptional achievement in maintaining a safe work environment, the National Safety Council (NSC) presented ABS with two safety awards. The NSC is a globally...

vfd