11 Nov 2020

The PARAT High Voltage Electrode Steam boiler will be installed at their power station in Weisweiler, Germany owned by RWE Power AG.

The PARAT IEH Electrode Steam Boiler has a 10kV connection with 23 barg Design Pressure and 220°C Design temperature. There will also be a superheater installed that is lifting the steam temperature. The Auxiliary Steam will be used for starting and shutting down a Power Plant block. The project for this Power to Heat plant will be done in cooperation with Kraftanlagen München. 

The RWE Power AG Power Station is a lignite-fired power station at Weisweiler in North Rhine-Westphalia that produces over 2100MW. The delivery date for the Power to Heat system at Weisweiler will be Q3 2021. This is the third order to PARAT Halvorsen AS from RWE Power AG in Germany.